Power Control Unit Grid Operator Configuration

Hello,
as controller for a photovoltaic plant i have an AXC F2152:
SOL-SA-PCU-41XX - Steuerung - 1114234 | Phoenix Contact,
with the following PLC project activated:
PLCnext Store | Power Control Unit

For communication with the grid operator an AXL F RS Uni 1H card is installed.
At the moment no communication with the grid operator is possible.
(communcation protocol: Beschreibung der fernsteuertechnischen Anbindung (n-ergie-netz.de)).

My questions:
Can you help me or provide an example with configuring the correct communication parameters for this grid operator?
Is there a manual(how-to) available which describes how other inverters(manufacturers) than the ones included in the „PCU Power Control Unit“ example plc project have to be implemented?

Thank you very much!

Hello, I understand that someone from your local Phoenix Contact office will be in touch with you to discuss this special application.
For other Community users with questions about the Power Control Unit app, please use the „Contact Developer“ button on the app page in the PLCnext Store.

Hello Martin,
thank you for the information and the tip.